Last updated: August 01. 2013 9:59PM - 907 Views

Story Tools:

Font Size:

Social Media:

Craig J. Opperman P.E., Scioto County Engineer, announced the work schedule for the week of Aug. 5, 2013 through Aug. 9, 2013 for his office.


ROAD IMPROVEMENT AND BRIDGE REPLACEMENT


Lick Run –Lyra Road – CR-2 from the 8.58 to the 8.78 mile marker in Vernon Township continues to be closed through Friday, August 30th, day and night. The location of the closure is between Edward Jones Road and Turkey Foot Township Road. County Engineer will be replacing a bridge in addition to raising and widening the road.


SITE DISTANCE IMPROVEMENT


Lick Run-Lyra Road – CR-2 from the 7.30 mile marker to the 7.49 mile marker in Vernon Township will be closed Monday, August 5th, through Friday August 9th, day and night. The location of the closure is between Turkey Foot Township Road and Schwamberger Road being 500 feet west to 500 feet north of the intersection with Clinton Furnace Road through the intersection. County Engineer will be improving intersection site distance.


ROAD CLOSURE


Rosemount Road – CR-377 in Clay Township continues to be closed through Friday, August 16th, day and night. The location of the closure is between State Route 139 and Heuter Hollow Road. J & H Structural Erectors will be installing sanitary lines for the Scioto County Sanitary Engineer’s Department.


CULVERT REPLACEMENT


Great Meadow Road – CR-51 at the 3.18 mile marker in Bloom Township will be closed Monday, August 5th, through Tuesday, August 6th, day and night. The location of the closure is between Webster Hope Road and Lick Run-Lyra Road. County Engineer’s Crews will be installing a concrete pipe.


Lintz Hollow Road – TR-179 at the 0.24 mile marker in Jefferson Township will be closed Wednesday, August 7th, from 8:00 A.M. until 4:00 P.M. The location of the closure is 100 feet south of South Marca Road. This is a no outlet road. County Engineer’s Crews will be installing a concrete pipe.


MOWING


Piketon Road in Madison Township, Caldwell Road in Valley Township, Big Run Road in Morgan Township


Big Bear Creek Road in Morgan and Rarden Townships, Arion Road in Union Township


Houston Hollow-Long Run Road in Clay, Jefferson and Valley Townships, Rosemount Road in Clay Township


Woods Ridge Road in Clay and Harrison Townships, Swauger Valley Road in Harrison Township


Greenbrier Road in Clay, Harrison and Jefferson Townships